Time plan
2025 is an important milestone in Copperstone’s history. Our goal is for the Viscaria mine to be in full production by then. The road that leads there is lined with important planning permits.

In Sweden, all mining operations are regulated by permit processes, from exploratory permits to land designation. In March 2022, we handed in our environmental permit application and during 2023 we expect to have an answer to the application. We’re simultaneously preparing our organisation and logistics to be ready to start if the application goes through. See Copperstone’s timeplan for reopening the Viscaria mine. (SV)